SPECIALIST SITE SERVICES - Shotcrete & Concrete Construction
SPECIALIST SITE SERVICES - Shotcrete & Concrete Construction
SPECIALIST SITE SERVICES - Shotcrete and Concrete Construction
Home
Services
Safety & Quality
Shotcrete profiles
Concrete Profiles
Rock Bolting profiles
Contact

 

Concrete Profiles

Structural Concrete Rehabilitation Works.
Pacific Highway Upgrade, Karuah to Buladelah.
Concrete Construction – Rail Line for Blasting Chamber.


Concrete Profile 1:

Project:
Structural Concrete Rehabilitation Works.
Client:
Newcastle Hunter Water Corporation.
Duration:
8 weeks.

Description:
Specialist Site Services was engaged to carry out structural rehabilitation of the Winding Creek stormwater channel. Years of erosion had caused Channel walls to move inwards.This created the possibility of damage to the surrounding properties. Hunter Water Corporation required stabilisation of channel walls and some floor panels. Access restrictions created difficulties for normal sized concrete trucks. All concrete was delivered in mini-mix trucks at 1.4m3 per delivery. Wet weather posed a continual problem with the stormwater levels rising very quickly as water was channeled from many branch channels.

The construction specification called for the excavation and removal of tree stumps, damaged channel walls, supply, placement and finishing of steel reinforced concrete footings and channel walls. The entire construction project required galvinised steel reinforcement and concrete footings for over 1km. The entire project was completed within the specified timeframe to the satisfaction of the client.

SPECIALIST SITE SERVICES - Concrete Profiles
Click image for larger version

Spraying SFRS from a boom lift to seal up areas of instability. This was carried out prior to allowing the access of workers.

 

SPECIALIST SITE SERVICES - Concrete Profiles
Click image for larger version

Cut and Cover section at western portal to Cross City Tunnel. Ironstone seam required 3mtr CT bolts and mesh prior to SFRS.

Top


Concrete Profile 2:

Project:
Pacific Highway Upgrade, Karuah to Buladelah.
Client:
Baulderstone Hornibrook.
Duration:
3 Months.

Description:
Specialist Site Services were awarded the contract to construct culverts along a 10 kms section of the Pacific Highway, north of Karuah. A total of 9 culverts were constructed for the highway upgrade. Specialist Site Services supplied the erection of all formwork and steel fixing as well as the placement/finish of concrete. All culvert excavation was carried out by sub-contractors prior to the laying of mud mats. All formwork used was marine ply shutters with all culverts requiring dowel joints and double layers of steel.

All concrete was batched at Boral’s Seaham Quarry some 40 minutes away from the construction site. All concrete deliveries were tested on-site to ensure that the strict specifications and concrete quality was adhered too. All formwork, steel fixing and concrete placement inspection and testing was carried out by Hyder Consulting and the Roads & Traffic Authority (RTA).

All works were interrupted by wet weather which required the removal of large volumes of water and mud from culvert areas ready for pouring. All formwork and steel reinforcing required washing down prior to any construction proceeding.

SPECIALIST SITE SERVICES - Concrete Profiles
Click image for larger version

Galvanised F82 sheets were lifted into place with a rough terrain crane. All individual panels required double mesh tied to dowels.

 

SPECIALIST SITE SERVICES - Concrete Profiles
Click image for larger version

All drilling, steel fixing and shotcrete was carried out from a man basket. A wood float finish was then applied to the wall surface.

Top


Concrete Profile 3:

Project:
Concrete Construction – Rail Line for Blasting Chamber.
Client:
Client Alstom Power.
Duration:
3 Weeks.

Description:
Alstom Power approached Specialist Site Services to carry out rockface stabilisation at their Telarah facility in the Hunter Valley. Upon completion of the work we were then asked to provide a price to construct a 50 metre concrete rail line. This rail line is to be used for moving large pieces of equipment from the main work site to the blast chamber.

The acceptance of our price and program meant that Specialist Site Services could begin demolition of existing rail line and concrete. A road saw was used to cut through the 600mm slab prior to removal with excavator/hammer. The work area was screened off to enable the client to continue working within the facility. All formwork, steel fixing and concrete was carried out by Specialist Site Services. The rail was poured in 3 sections at 600mm think by 5 metres wide. The rail sections were fitted by Alstom prior to Specialist Site Services grouting the entire rail section. The work was completed well within the program and to the clients satisfaction.

SPECIALIST SITE SERVICES - Concrete Profiles
Click image for larger version

Placing blinding layer for rail section of blast chamber project.

 

SPECIALIST SITE SERVICES - Concrete Profiles
Click image for larger version

Freshly placed concrete for rail section of blast chamer project.

Top


Go to the top

Copyright©2006 SPECIALIST SITE SERVICES, Australia, All rights reserved
Website designed by MaoWebstyle