Rockbolting Profiles
Soil Nail Stabilisation – Putty Road,
Howes Valley.
Rock Face Stabilisation – Mt Keira, Wollongong.
Stabilisation of Excavated Construction Site.
Rockbolting Profile 1:
- Project:
- Soil Nail Stabilisation – Putty Road, Howes Valley.
- Client:
- Roads and Traffic Authority.
- Duration:
- 1 week.
Description:
Specialist Site Services were engaged by the Roads
and Traffic Authority to drill and place 50 soil nails on
the Putty Road within the Yengo National Park. The galvanised
soil nails were 3 metres in length and consisted of plastic
corrugated sheath for added corrosion protection. The lane
closure and traffic control was carried out by the RTA. The
drill area was around a road culvert that appeared to be failing
internally creating a wash-out area on the road embankment.
The area had been temporarily stabilised with cement bags
years before, but this was also failing. SSS suggested the
entire area be sprayed with Steel Fibre Reinforced Steel (SFRS)
immediately prior to any drilling commenced.
The drilling was difficult due to the fragile
nature of the rock causing most holes to immediately collapse
when retracting the drill steels. The mesh installed was galvanised
F81 before 200mm of 40mpa shotcrete. All drilling, grouting,
meshing and shotcreting was carried out from a boomlift. The
work also included a shotcrete spillway to be constructed
and included a concrete energy dissipater. All works were
completed within time and to the total satisfaction of the
client.

Click image for larger version
Embankment Stabilisation below road
level and with difficult access. |
|

Click image for larger version
Drilling for soil nails from Boom
lift. Drilling was difficult due to fragile nature of
rock. |
Top
Rockbolting Profile 2:
- Project:
- Rock Face Stabilisation – Mt Keira, Wollongong.
- Client:
- Wollongong City Council.
- Duration:
- 5 Weeks.
Description:
Specialist Site Services were awarded the tender
for the stabilisation of rock face areas over hanging the
scenic road on Mt Keira. A 5km section of road was closed
daily to traffic from 7am to 5pm, Monday to Friday. The stabilisation
work undertaken included devegetation, rock removal and scaling,
grooming of batters, rockbolting, shotcreting and drainage.
All vegetation was chipped and sent to the council depot for
use within the shire. All excavated materials (scaling/grooming)
approximately 300m3 were used in conjunction with the National
Parks and Wildlife on their walking trails and to block unauthorised
access trails.
The majority of scaling was carried out using
a longreach excavator, 30 tonne excavator/hammer and manually
from Elevated Work Platforms. Blasting mates were used on
the roadway to minimise damage from scaled rock. Specialist
Site Services drilled and placed over 60 rock bolts ranging
from 3 metres to 6 metres at heights of 30 metres above the
roadway. There was over 1000m2 of coloured shotcrete sprayed.
All health, safety and environmental issues were managed by
Specialist Site Services to the total satisfaction of the
client.

Click image for larger version
Drilling from Elevated Work Platform. |
|

Click image for larger version
Scaling of rockface above a scenic
roadway using a longreach excavator. |
Top
Rockbolting Profile 3:
- Project:
- Stabilisation of Excavated Construction Site.
- Client:
- Danny Smith Professional Building.
- Duration:
- 5 weeks.
Description:
Specialist Site Services were engaged by a local
builder to stabilise a benched excavation overlooking Scenic
Drive, Merewether. The geotechnical engineer specified over
100 x 3 metre thread bar rockbolts. All bolts were stressed
to 20t prior to fixing a double layer of F82 mesh. All drilling
was carried out from a boomlift with rotary percussive rock
drills and airlegs.
Due to the position of the development, drilling
was restricted to the hours between 7.30am and 3.00pm. All
shotcrete was sprayed from the basket of a boomlift with the
bottom lift (ground floor) requiring a wood float finish.
The 2 levels above required a gun finish only. Due to the
design of the development, mine subsidence requirements called
for a number of vertical footings up to 4 metres high. These
were all sprayed in by starting from the ground. All shotcrete
sprayed was 32mpa. The project is still a work in progress
with all work to the clients satisfaction.

Click image for larger version
Stressing of rockbolts prior to fixing
F82 mesh. |
|

Click image for larger version
Placing a chemical anchor for immediate
support. |
Top
|