SPECIALIST SITE SERVICES - Shotcrete & Concrete Construction SPECIALIST SITE SERVICES - Shotcrete & Concrete Construction
SPECIALIST SITE SERVICES - Shotcrete and Concrete Construction
Home
Services
Safety & Quality
Shotcrete Profiles
Concrete profiles
Rock Bolting profiles
Contact

 

Shotcrete Profiles

Fibre Reinforced Shotcrete - Cross City Tunnel Project, Sydney.
Structural Rehabilitation Works – Newcastle Ocean Baths.
Mt.Owen Mine (R.O.M) Dump Station Project.


Shotcrete Profile 1:

Project:
Fibre Reinforced Shotcrete - Cross City Tunnel Project, Sydney.
Client:
Baulderstone Hornibrook / Bilfinger Berger.
Duration:
(15 months) Proposed completion 2005.

Description:
Specialist Site Services was engaged to carry out structural shotcrete stabilisation of the Darling Harbour off-ramps, cut/cover sections, ventilation shafts, tunnel rib and roof. The specification called for the application of SFRS (steel fibre reinforced shotcrete) to all areas. SFRS was used for stabilising all permanent / temporary excavations, contiguous piling and the final lining of cuttings to a minimum thickness of 75mm.

The sprayed areas consisted of mainly fractured/faulted sandstone including ironstone seams with minimal ground water ingress. Some ironstone seams that were sprayed with SFRS included placing rockbolts and mesh.

Several means of shotcrete delivery were required due to access difficulties such as piggy backing a line pump on the surface direct to the shotcrete rig, lowering kibbles of shotcrete down a vent shaft directly to the shotcrete rig. The frequency of shotcrete deliveries from the nearest batch plant was problematic due to the traffic congestion of Sydney. The mix specification would not allow the use of hydration inhibitors meaning our specialist shotcrete crews were kept continually on alert.

SPECIALIST SITE SERVICES - Shotcrete Profiles
Click image for larger version

Spraying SFRS from a boom lift to seal up areas of instability. This was carried out prior to allowing the access of workers.

 

SPECIALIST SITE SERVICES - Shotcrete Profiles
Click image for larger version

Cut and Cover section at western portal to Cross City Tunnel. Ironstone seam required 3mtr CT bolts and mesh prior to SFRS.

Top


Shotcrete Profile 2:

Project:
Structural Rehabilitation Works – Newcastle Ocean Baths.
Client:
Newcastle City Council.
Duration:
1 week.

Description:
Specialist Site Services was engaged to carry out structural repair work to the southern promenade of the Newcastle Ocean Baths. The southern wall of the Ocean Baths had collapsed during heavy seas. The heavy seas scoured out underneath the promenade requiring the immediate closure of the baths to the public. The Newcastle Council used excavators to remove the damaged concrete wall enabling us to underpin the promenade with shotcrete.

The design engineers specified stainless steel reinforcement for the entire wall. The wall dimensions were 50 metres x 1.6 metres x 0.8 metres thick, all requiring shotcrete placement of 50mpa concrete. Shotcrete was specified due to the continual flooding of the promenade by heavy seas. Due to the thickness and the length of the wall it was sprayed and float finished in 5 metre bays. The was carried out by spraying alternative bays and curing with a wax based curing agent. The entire project was completed to the satisfaction of the design engineers and the Newcastle City Council.

SPECIALIST SITE SERVICES - Shotcrete Profiles
Click image for larger version

Placing 50mpa shotcrete Note: stainless steel reinforcement.

 

SPECIALIST SITE SERVICES - Shotcrete Profiles
Click image for larger version

Spraying of alternative bays and finish of construction of ocean baths walls.

Top


Shotcrete Profile 3:

Project:
Mt.Owen Mine (R.O.M) Dump Station Project.
Client:
Roche Mining(JR) Pty Limited.
Duration:
15 Days.

Description:
Specialist Site Services were called in to drill, mesh and shotcrete both wing walls adjacent to the dump station. The scope of work called for the grooming of large areas including the placing of strip drain and galvanised mesh prior to drilling being carried out. All mesh was placed and stitched manually by our shotcrete team working with retractable harnesses. The reinforcing mesh was secured to both embankments by pattern drilling and placing of galvanised dowels. All dowels were fully cement grouted prior to placing shotcrete.

Drilling was carried out from a 120ft boom which enabled our team to complete 2/3 of the work, the rest was completed on foot in retractable harnesses. The same work method was applied for the shotcrete, with the majority being placed out of the boom and the rest by hand and harness. All work was completed to the satisfaction of the client and within the timeframe required.

SPECIALIST SITE SERVICES - Shotcrete Profiles
Click image for larger version

The dump station nears completion with some fine tuning being carried out prior to shotcrete. Notice drainage beneath mesh.

 

SPECIALIST SITE SERVICES - Shotcrete Profiles
Click image for larger version

The shotcrete team needed to spray large areas from the ground. The slope angle proved hard work for the shotcrete team.

Top


Go to the top

Copyright©2006 SPECIALIST SITE SERVICES, Australia, All rights reserved
Website designed by MaoWebstyle