Emergency landslip remediation and culvert repair works were completed by Specialist Site Services on the north coast of New South Wales following a severe weather event. A landslip affected drainage infrastructure along this regional road. The project scope and design were for the stabilisation of the existing culvert and the reinstatement of a large area of dirt pavement which was washed away.
Key components of the project included:
- Design and Construct contract
- Development and implementation of WHS, Quality and Environmental management plans
- Traffic management
- Drilling and installation of mini piles
- Drilling and installation of hollow bar soil nails
- Form wall and footing
- Meshing of wall and footing
- Spraying of shotcrete wall
- Backfill and reinstatement of pavement road
- Soil nail grout testing and concrete testing
Project Duration: Construction phase 4 weeks